Client - Red Stag Timber Date - 2019Drying more than 400,000 m³ of timber each year with energy from Red Stag Timber‘s own biofuels, their seven kilns operate 24/7.
Red Stag required additional heating capacity for steam generation for kiln #3 and added a steam header system to one of their wood-fired boilers. GRIT was engaged to provide the mechanical design for the steam pipework and structural design for the pipe supports.